We are over budget

Spending is ahead of value earned, or the forecast exceeds the budget.

First 24 hours

  1. Calculate CPI and a forecast at completion.
  2. Separate one-off events from a pattern.
  3. Check commitments not yet invoiced.

Then

  1. Find the cause: estimates, scope, rate or rework.
  2. Use contingency only for what it was meant to cover.
  3. Reduce scope or renegotiate.
  4. Ask for more funding with a revised case, if it’s still worthwhile.
Message you can adapt

At 55% complete we’ve spent 68% of the budget. At the current rate we’ll finish €26k over. Main cause: more rework in integration. Options are attached; I recommend cutting the reporting module.

Avoid

Don’t hope a low CPI will recover by itself. It rarely does.