Earned Value Management (EVM)

Earned Value Management (EVM): tells objectively whether the project is on time and on budget — and where it will land.

Best for: Budgeted, measurable projects · Time: 15 min per report
Domain: Finance · Focus area: Monitoring and Controlling

PV · Planned valueBudget of work that should be done by now
EV · Earned valueBudget of work actually done
AC · Actual costWhat that work really cost
SPI = EV ÷ PV
CPI = EV ÷ AC
Forecast = Budget ÷ CPI

How it works

EVM compares three numbers at a given date. An index of 1 means on plan; below 1 means behind schedule (SPI) or over budget (CPI). The CPI also predicts the final cost.

  • SPI < 1: less work done than planned.
  • CPI < 1: the work done cost more than budgeted.
  • Trends over several periods matter more than one value.

How to apply it

  1. Give each work package a budget — the total is your BAC.
  2. At each reporting date, estimate % complete per package → EV.
  3. Get actual costs (AC) from finance or timesheets.
  4. Compute SPI, CPI and the forecast (try it below).
  5. Act when an index drops below ~0.9, and show the trend in your status report.

Try it

In practice

Budget €100k; €50k of work planned, €40k worth done, €45k spent → SPI 0.80, CPI 0.89, forecast ≈ €112.5k.

Pro tip

Use simple rules for % complete (0% / 50% / 100%) to avoid the “90% done for weeks” trap.

Use it

Quick check

EV = 40k, AC = 45k, so CPI = 0.89. What does it tell you?