Budget and Reserves

Budget and Reserves: builds a budget that survives contact with reality.

Best for: After estimating · Time: Half a day
Domain: Finance · Focus area: Planning

How it works

The cost baseline is your approved, time-phased budget. Contingency reserve covers identified risks and sits inside it. Management reserve covers surprises, sits outside it and needs management’s approval to use.

  • Contingency: known-unknowns.
  • Management reserve: unknown-unknowns.
  • Check timing against funding limits.

How to apply it

  1. Add up estimates by work package.
  2. Add contingency based on the risk register.
  3. Time-phase it, month by month.
  4. Agree management reserve with the sponsor.
In practice

Work €180k + contingency €20k = baseline €200k. Plus €15k management reserve = budget €215k.

Pro tip

Show reserves openly. Hidden padding in every task gets spent; a visible reserve gets managed.

Use it

Quick check

An identified supplier risk is funded from…

Sources

  • PMBOK® Guide, 8th edition, and The Standard for Project Management (PMI, 2025)

Last reviewed 2026-11-02 against the PMBOK® Guide, 8th edition · Practitioner review pending · How this guide is made