Benefits Realization Plan

Benefits Realization Plan: tracks whether the promised value actually arrives, often months after delivery.

Best for: Any project justified by outcomes · Time: 2–4 hours
Domain: Governance · Focus area: Planning

How it works

Delivering the output isn’t the same as getting the benefit. This plan lists each benefit, how it will be measured, its starting value, its target, the date and the person in the business who owns it.

  • Measure a baseline before anything changes.
  • Give each benefit an owner outside the project team.
  • Book the review date before the project closes.

How to apply it

  1. List benefits from the business case.
  2. Pick one measure for each, and record today’s value.
  3. Set target, date and owner.
  4. Hand the plan to the owner at closure and schedule the review.
In practice

Benefit: fewer support calls. Baseline 1,200 a month, target 960 by December, owner: head of support.

Pro tip

A benefit with no owner after the project closes is a wish.

Use it

Quick check

Who should own a benefit after the project closes?