RAG Status Report

RAG Status Report: gives leadership a status they can read in 30 seconds, and the decisions they must take.

Best for: Weekly or bi-weekly reporting · Time: 20 minutes
Domain: Governance · Focus area: Monitoring and Controlling

AreaStatusComment
ScheduleAmberTesting 4 days late, overtime planned
BudgetGreenCPI 0.98
ScopeGreenNo open change requests
RisksRedSupplier may miss delivery, decision needed
TeamGreenFully staffed
Top of the report: “Decisions needed from you”. Every amber or red line has an action and an owner.

How it works

A one-page report that rates the key dimensions — schedule, budget, scope, risks, team — as Red, Amber or Green, with one line of evidence each, plus highlights, next steps and decisions needed.

  • Green: on track. Amber: issue the team can recover. Red: needs escalation or a decision.
  • Thresholds are agreed in advance (e.g. Amber = up to 10% slippage).
  • Trends (↑ ↓) add context to the colours.

How to apply it

  1. Agree the RAG thresholds with the sponsor at kick-off.
  2. Each week, rate every dimension with one line of evidence (use SPI/CPI if you have them).
  3. Give every amber or red line a recovery action and an owner.
  4. Put “Decisions needed” at the very top.
  5. Send it on a fixed day so people know when to expect it.
Pro tip

Beware the “watermelon” report — green outside, red inside. Reporting amber early builds more trust than a surprise red.

Use it

Quick check

A report that looks green while the project is red inside is called a…

Sources

  • PMBOK® Guide, 8th edition, and The Standard for Project Management (PMI, 2025)

Last reviewed 2026-11-02 against the PMBOK® Guide, 8th edition · Practitioner review pending · How this guide is made