Agile Delivery · tool 6 of 6
Burndown and Burnup Charts
Burndown and Burnup Charts: shows progress and scope change at a glance.
Best for: Tracking iterations and releases · Time: 5 min a day
Domain: Schedule · Focus area: Monitoring and Controlling
How it works
A burndown shows work remaining. A burnup shows work completed against total scope. Burnups are better when scope changes, because the top line moves visibly.
- Burnup makes scope creep visible.
- Count only finished work.
- Look at the trend, not the day.
How to apply it
- Choose hours or points.
- Update it from the board.
- Discuss the trend.
- Show scope changes openly.
In practice
Progress looks flat on a burndown, but the burnup shows scope grew 30%.
Pro tip
Use a burnup with stakeholders. It answers “why isn’t it finished yet?” honestly.
Use it
- Playbook: Scope keeps growing
Quick check
Which chart best shows scope growth?
Sources
- PMBOK® Guide, 8th edition, and The Standard for Project Management (PMI, 2025)
Last reviewed 2026-11-02 against the PMBOK® Guide, 8th edition · Practitioner review pending · How this guide is made