Story Points and Velocity

Story Points and Velocity: forecasts adaptive work from what the team has really done.

Best for: Release planning · Time: Ongoing
Domain: Schedule · Focus area: Planning

How it works

Points express relative size. Velocity is how many points the team finishes per iteration. After a few iterations, it gives an evidence-based forecast. It only makes sense within one team.

  • Never compare velocity across teams.
  • Use a range, not an average alone.
  • Velocity isn’t a target; pushing on it makes it meaningless.

How to apply it

  1. Size items against a reference.
  2. Record what’s completed.
  3. Take the recent range.
  4. Divide the remaining work by it.
In practice

200 points left at 20–25 per sprint means 8–10 sprints.

Pro tip

The moment velocity becomes a target, it stops being a measure.

Quick check

Velocity is best used for…