Work Breakdown Structure (WBS)

Work Breakdown Structure (WBS): breaks the total scope into small, manageable pieces of work that can be estimated and owned.

Best for: Planning the scope · Time: 2–4 hours
Domain: Scope · Focus area: Planning

0 Website launch
1 Design
1.1 Wireframes
1.2 Visual design
2 Content
2.1 Copy
2.2 Images
3 Build
3.1 Front-end
3.2 Back-end
4 Launch
4.1 Testing
4.2 Go-live
Deliverables (outlined) break down into work packages (grey) that one person can estimate and own.

How it works

A hierarchical tree: the final deliverable at the top, broken into major deliverables, then into work packages — the smallest unit you can estimate, assign to one owner and track.

  • 100% rule: the children of each box add up to exactly 100% of the parent — nothing missing, nothing extra.
  • Describe deliverables (nouns), not activities (verbs).
  • Stop splitting when a package takes roughly 1–10 days of effort.

How to apply it

  1. Write the final deliverable in the top box.
  2. Split it into 3–7 major deliverables or phases, with the team in the room.
  3. Keep breaking down each branch until every package can be estimated and given to one owner.
  4. Number every box (1.1, 1.2.3…) and reuse those numbers in your schedule, budget and RACI.
In practice

Website launch → 1 Design, 2 Content, 3 Build, 4 Launch → 3.1 Front-end, 3.2 Back-end…

Pro tip

Use sticky notes on a wall first. It’s faster to move paper than to restructure a file — and the team owns what it builds.

Use it

Quick check

What does the 100% rule say?

Sources

  • PMBOK® Guide, 8th edition, and The Standard for Project Management (PMI, 2025)

Last reviewed 2026-11-02 against the PMBOK® Guide, 8th edition · Practitioner review pending · How this guide is made