Playbook
We are going to miss the date
Milestones keep slipping, or the forecast no longer reaches the deadline.
First 24 hours
- Stop guessing: get a real forecast from those doing the work.
- Check the critical path and remaining float.
- Find out what truly fixes the date: a contract, an event, or a preference.
- Tell the sponsor today, with options.
Then
- Cut or defer scope first. It’s usually the cheapest way to win time.
- Compress only critical tasks, choosing the cheapest day saved.
- Replan with the team and rebaseline formally.
Message you can adapt
We now forecast 12 June, not 30 May. Main cause: testing found more integration defects than planned. Options: A) drop the export and keep 30 May, B) keep scope and move to 12 June, C) add a contractor for €9k and land on 5 June. I recommend A. I need a decision by Friday.
Avoid
Don’t promise to “catch up” without a change to scope, resources or dates.