Monte Carlo Simulation

Monte Carlo Simulation: replaces one date with a range and a probability.

Best for: Large schedules and budgets · Time: Half a day with a tool
Domain: Risk · Focus area: Monitoring and Controlling

How it works

A simulation runs the plan thousands of times, varying durations and costs within estimated ranges. The output tells you the chance of finishing by each date.

  • Quality depends on the input ranges.
  • Include correlated risks.
  • Report confidence levels, such as P80.

How to apply it

  1. Give key tasks a three-point range.
  2. Add major risks.
  3. Run the simulation in your tool.
  4. Report the dates at P50 and P80.
In practice

The plan says June. The simulation gives 15% by June and 80% by mid-August.

Pro tip

“80% confident by August” is a stronger promise than “June, hopefully”.

Use it

Quick check

What does P80 mean?