Schedule · tool 2 of 7
Critical Path Method (CPM)
Critical Path Method (CPM): finds the chain of tasks that sets the project’s end date — the tasks you can’t let slip.
Best for: Deadline-driven projects · Time: 1–2 hours
Domain: Schedule · Focus area: Planning
How it works
Tasks and their dependencies form a network. The critical path is the longest chain through it: its tasks have zero “float” (slack), so any delay on them delays the whole project.
- Forward pass: earliest start and finish of each task.
- Backward pass: latest start and finish without moving the end date.
- Float = latest start − earliest start. Zero float = critical.
How to apply it
- List activities with durations and predecessors (your Gantt already has them).
- Let your tool compute — or calculate — earliest and latest dates.
- Highlight zero-float tasks and give them your best people and closest follow-up.
- To finish earlier, shorten critical tasks only: add resources (crashing) or overlap tasks (fast-tracking).
Adding a developer to a non-critical task costs money and gains nothing. Adding one to a critical task can move the end date.
The critical path changes as work progresses. Re-check it every time you update the schedule.
Use it
- Playbook: We are going to miss the date
Quick check
Task C has 3 days of float and slips 2 days. What happens to the end date?