Crashing and Fast Tracking

Crashing and Fast Tracking: shortens a schedule when the date can’t move.

Best for: Recovering a late project · Time: 1–2 hours
Domain: Schedule · Focus area: Monitoring and Controlling

How it works

Crashing adds resources to critical tasks and raises cost. Fast tracking runs tasks in parallel that were planned in sequence, which raises risk and rework. Neither is free, and both only help on the critical path.

  • Only compress critical tasks.
  • Pick the cheapest day saved first.
  • Adding people late can slow things down.

How to apply it

  1. Find the critical path.
  2. List each way of saving a day and its cost or risk.
  3. Choose the best trade.
  4. Recheck the path, as it can move.
In practice

Bring in a second electrician for €2k to save three days, rather than start testing before the install ends.

Pro tip

Before compressing, try cutting scope. It’s often the cheapest way to win time.

Use it

Quick check

Doing two tasks in parallel that were planned one after the other is…