Risk · tool 1 of 7
Risk Register & Heat Map
Risk Register & Heat Map: identifies what could go wrong early, and decides what to do before it happens.
Best for: Every project · Time: Workshop + 15 min/week
Domain: Risk · Focus area: Planning
How it works
A living log of risks. Each risk is scored on probability and impact (1–5); the product gives a priority score plotted on a heat map. Each significant risk gets a response and an owner.
- Write risks as “Because of [cause], [event] may occur, leading to [effect]”.
- Responses: Avoid, Reduce, Transfer (insurance, contract) or Accept.
- Columns: ID, risk, P, I, score, response, owner, due date, status.
How to apply it
- Run a 60-minute risk workshop using the WBS, assumptions and lessons from past projects.
- Write each risk in cause–event–effect form.
- Score probability and impact, and plot them on the heat map.
- Every red risk gets a response, an owner and a date.
- Review the top 5 risks in every status meeting; rescore or close them.
“Because our supplier has one factory, a production stop may occur, delaying hardware delivery by 6 weeks.” P3 × I5 = 15 → find a second supplier (Reduce).
A risk register that is only filled at kick-off is a document, not a tool. The weekly review is what makes it work.
Use it
- Template: Risk Register (blank), filled example
Quick check
Probability 3, impact 5. What is the score, and what do you do?