Schedule · tool 7 of 7
Reference Class Forecasting
Reference Class Forecasting: corrects optimism by using what happened on similar projects.
Best for: Estimating large or unfamiliar work · Time: 1–3 hours
Domain: Schedule · Focus area: Planning
How it works
People estimate from the inside, picturing how the work should go. This is the planning fallacy. Reference class forecasting takes the outside view: look at how comparable projects actually turned out, and start there.
- Choose a class of truly similar projects.
- Use their actual results, not their plans.
- Adjust only for documented differences.
How to apply it
- Find five to ten comparable projects.
- Record planned versus actual time and cost.
- Take the typical overrun.
- Apply it to your estimate before adjusting.
Your last eight website launches overran by 15–40%. A 10-week plan is more honestly 12–14 weeks.
Keep a simple record of estimates against actuals. In a year it will beat anyone’s judgment.
Use it
- Case study: Berlin Brandenburg Airport
- Case study: Crossrail (Elizabeth line)
Quick check
What does the outside view rely on?
Sources
- D. Lovallo and D. Kahneman, “Delusions of Success”, Harvard Business Review (2003)
- B. Flyvbjerg and D. Gardner, How Big Things Get Done (2023)
Last reviewed 2026-11-02 against the PMBOK® Guide, 8th edition · Practitioner review pending · How this guide is made