Schedule · tool 3 of 7
PERT · Three-point Estimation
PERT · Three-point Estimation: produces realistic estimates when there’s uncertainty, and turns one fragile date into a range.
Best for: Uncertain or new work · Time: Minutes per task
Domain: Schedule · Focus area: Planning
Expected = (O + 4M + P) ÷ 6
σ = (P − O) ÷ 6
σ = (P − O) ÷ 6
How it works
For each task you ask for three estimates: Optimistic (O), Most likely (M) and Pessimistic (P). The weighted average gives a realistic expected duration, and the spread tells you how uncertain it is.
- M counts four times, so one extreme guess doesn’t dominate.
- σ (standard deviation) measures uncertainty: the bigger, the riskier.
- Expected ± σ covers about 68% of outcomes; + 2σ about 95%.
How to apply it
- Ask the person who will do the work for O, M and P — not the manager.
- Compute the expected value and σ (try it below).
- Use the expected value in the schedule; add buffer on the critical path based on the σ values.
- Communicate ranges: “10 to 14 days, most likely 12” rather than a single promise.
Try it
Pro tip
A very wide gap between O and P is a signal: break the task down further or run a quick spike to learn more.
Quick check
O = 4, M = 6, P = 14 days. What is the expected duration?